Upper Mugu Karnali

Upper Mugu Karnali Hydropower Project (306 MW)

Location: Chhayanath Rara Municipality and Mugum Karmarong Rural Municipality, Mugu district, Karnali Province
Developer: Elevate Energy Pvt. Ltd.
Geological Setting: Higher Himalaya
Involvement Stage: Feasibility Study
Duration: May 2021 – present

Lower Apsuwa

Lower Apsuwa Hydropower Project (54 MW)

Location: Silichong Rural Municipality and Makalu Rural Municipality, Sankhuwasabha district, Province 1
Developer: Mizu Energy Pvt. Ltd.
Geological Setting: Lesser Himalaya
Involvement Stage: Detail Design/Construction
Duration: May 2021 – present

Karuwa Seti Hydropower Project (32 MW)

Location: Machhapuchhre Rural Municpality, Kaski district, Gandaki Province
Developer: Jhyamolongma Hydropower Development Company Pvt. Ltd.
Geological Setting: Higher & Lesser Himalaya
Involvement Stage: Detail Design/Construction
Duration: (August 2018 – March 2019); (January 2021 – July 2021)

Kaligandaki Storage

Kaligandaki Storage Hydropower Project (844 MW)

Location: Baglung, Parbat districts (Gandaki Province) & Gulmi district (Lumbini Province)
Developer: Department of Electricity Development; Government of Nepal
Geological Setting: Lesser Himalaya
Involvement Stage: Feasibility Study
Duration: (January 2020 – present)